Dell, HPE, Lenovo and Supermicro are asking customers to pay 25% to 45% more for Nvidia-powered AI servers — months after contracts were signed and, in some cases, right before delivery — according to a Financial Times investigation that puts a hard number on how brutally the memory shortage is rewriting the AI infrastructure business.

The retroactive surcharges are being levied on orders already placed at agreed prices. JPMorgan research puts memory costs at more than 400% above early-2024 levels and expects DRAM to keep climbing through the end of 2026; GPU servers are reported to be at least 20–30% more expensive to build, while memory-heavy CPU nodes have roughly tripled in cost because DRAM makes up such a large share of the bill of materials. A worldwide shortage of printed circuit boards, forecast to last until 2028, adds further pressure.

The practice is already in court. Trading firm XTX Markets sued Dell in Ireland in June over a $549 million order for 1,680 servers, having paid $5 million extra for a guaranteed price; court documents show Dell later demanded at least $62–70 million more, an 11.3–12.8% premium on the base price. Dell says component costs surged and denies wrongdoing. HPE, meanwhile, rewrote its terms of sale so it can reprice orders between purchase and delivery — a change CEO Antonio Neri has defended as protecting margins.

Customers are paying anyway, sources told the FT, because compute is business-critical. The hit falls hardest on quant trading shops such as Jane Street, Optiver and Hudson River Trading, and on neocloud providers like CoreWeave and Nscale, which borrow against fixed customer contracts. Hyperscalers such as Microsoft, Amazon and Alphabet can absorb procurement costs more flexibly. The episode follows Bloomberg's report of Nvidia's 15%-plus price increases and caps a year in which the AI memory bill has rippled out to everything from PC prices to Christmas retail.